Person |
Organization |
Role |
---|---|---|
Mike Conlon |
PI |
Sponsor |
Valrie Davis |
MSL |
Sponsor |
Narayan Raum |
CTRIP |
Project Manager |
Christopher Barnes |
CTRIP |
Harvester Project Manager |
James Pence |
CTRIP |
Harvester Technical Contact |
Alex Rockwell |
MSL |
Implementation Expert |
Logan Clapp |
MSL |
Implementation Expert |
Nick Dunham |
DSR |
Data source |
Person |
FTE |
---|---|
Mike Conlon |
.05 |
Valrie Davis |
.1 |
Narayan Raum |
.25 |
Christopher Barnes |
.1 |
James Pence |
.25 |
Alex Rockwell |
.66 |
Item |
Start Date |
Finish Date |
---|---|---|
Project Start |
4/22/2011 |
4/22/2011 |
Project Plan |
4/25/2011 |
4/29/2011 |
Discovery |
5/2/2011 |
5/6/2011 |
Design |
5/9/2011 |
5/13/2011 |
Build |
5/16/2011 |
5/27/2011 |
Dev Implementation |
5/30/2011 |
6/3/2011 |
Staging Implementation |
6/6/2011 |
6/10/2011 |
Production Implementation |
6/13/2011 |
6/17/2011 |
Contribute Source to SF Site |
6/20/2011 |
6/24/2011 |
Monitor Harvesting |
6/20/2011 |
6/24/2011 |
Project Complete |
6/24/2011 |
6/24/2011 |