DateMilestoneWhat it means
(tick)  Friday, January 19, 2024Deadline for feature pull requestsIf you wish to contribute features to DSpace 8.0, you must submit a pull request by this date.
(tick)  Friday, February 9Feature PR Review/Test DeadlineInitial reviews/testing of PRs should be completed by all assigned reviewers.
(tick)  Friday, February 23
Feature PR Merge Deadline (Feature Freeze)DSpace 8.0 is considered feature-complete on this date. All Feature PRs should be merged. Only bug fixes will be pulled between this date and final release.
February 26- March 15Major dependency updatesThis is a period where the codebase will undergo major updates to support latest versions of Spring (supporting Jakarta EE) and Angular.
March 18-22Early documentation / bug fixesCode cleanup prior to Release candidate.
By Friday, March 29
Release Candidate 1 taggedA DSpace 8.0 Release Candidate will be available for wider testing.
April 1-12
TestathonIntensive public testing of the 8.0 Release Candidate is invited.  The Release Team will focus on getting problems resolved.
Friday, April 26Deadline for bug-fix pull requestsBug fixes should ideally be submitted by this date.
Friday, May 3Bug-Fix PR Merge Deadline (Code Freeze)Ideally all bug fixes are merged by this date.  Code is "frozen", with exceptions only made if major issues are discovered.
May 6-10Final Cleanup / DocumentationThis week is set aside for any final cleanup (or very late bug fixes) that need to be applied to the code.  Also used to finalize Documentation, Release Notes, etc.