Comment: Update timelines based on OR16 talks, etc

...

Timeframe: 3rd and 4th Quarters of 2015. The UI platform will be selected before the end of 2015OR2016.

...

Timeframe: Organized development begins in January July 2016, and continues until 7.0 Release in late 20162017.

  •  [December 2015July 2016] : Establish a development team (ideally with some overlap with the planning phase team). This team will likely consist of volunteer or "donated" development resources
  •  [January July 2016 - May 2017] : Schedule a series of development "sprints" which will begin in early mid-2016. This will allow institutions to donate developers for specific sprints (or allow developers to balance local work with sprint work)
    •  Ideally, hold a "hackathon" to help kickstart some of these sprints and get everyone on the same page?
    •  Development process will be kept transparent (on GitHub) with ongoing status reports to Committers, etc.
    •  Ongoing "beta" or early releases will be made available for testing/feedback/analysis by developers and/or DCAT members
  •  [June 20162017] : Early / Beta version of the new UI is presented at the OR2016 conference in Dublin. IdeallyOR2017. Ideally, we'd not only have a demo, but also a training session also hold training sessions on the new UI.
  •  [Late 20162017] : Fully functional new UI in place for the DSpace 7.0 release (tentatively scheduled for Late 20162017).