The objectives of sprint-03 are to:

  1. Address Phase-1 issues
    1. Pairtree...
    2. Integration tests...
    3. All "red" tickets:
      Jira
      serverDuraSpace JIRA
      jqlQueryproject = FCREPO AND status in (Open, "In Progress", Reopened, "In Review", Received) AND component = f4-import-export AND labels = import-export-phase-1 ORDER BY priority DESC
      serverIdc815ca92-fd23-34c2-8fe3-956808caf8c5
      ...
  2. Implement Phase-2 requirements for verification tooling 
  3. ...
  4. Implement Phase-2 requirements
    1. Support export of resource and its "members" based on a user-provided membership predicate
    2. BagIt??
    3. All "red" tickets:
      Jira
      serverDuraSpace JIRA
      jqlQuerylabels = import-export-phase-2 ORDER BY priority DESC
      serverIdc815ca92-fd23-34c2-8fe3-956808caf8c5
  5. Plan the production of Produce a few 3-minute videos that demonstrate import/export functionality

...