Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: 8.0 Testathon delayed by a week, shifting all deadlines back

...

DateMilestoneWhat it means
(tick)  Friday, January 19, 2024Deadline for feature pull requestsIf you wish to contribute features to DSpace 8.0, you must submit a pull request by this date.
(tick)  Friday, February 9Feature PR Review/Test DeadlineInitial reviews/testing of PRs should be completed by all assigned reviewers.
(tick)  Friday, February 23
Feature PR Merge Deadline (Feature Freeze)DSpace 8.0 is considered feature-complete on this date. All Feature PRs should be merged. Only bug fixes will be pulled between this date and final release.
February 26March 3 - March 1529Major dependency updatesThis is a period where the codebase will undergo major updates to support latest versions of Spring (supporting Jakarta EE) and Angular.
March 18-22April 1 - April 5Early documentation / bug fixesCode cleanup prior to Release candidate.
By Friday, March 29April 5
Release Candidate 1 taggedA DSpace 8.0 Release Candidate will be available for wider testing.
April 18-1219
TestathonIntensive public testing of the 8.0 Release Candidate is invited.  The Release Team will focus on getting problems resolved.
Friday, April 26May 3Deadline for bug-fix pull requestsBug fixes should ideally be submitted by this date.
Friday, May 310Bug-Fix PR Merge Deadline (Code Freeze)Ideally all bug fixes are merged by this date.  Code is "frozen", with exceptions only made if major issues are discovered.
May 613-1017Final Cleanup / DocumentationThis week is set aside for any final cleanup (or very late bug fixes) that need to be applied to the code.  Also used to finalize Documentation, Release Notes, etc.
Monday, May 1320, 2024 DSpace 8.0 is publicly releasedDSpace 8.0 is released for download and general use.

...