titleMeeting 04 - 2017-05-26

Meeting 04 - 2017-05-26

  • 11am ET

Attendees

Agenda

  1. Retrospective, from a process perspective...
    1. What went well?
    2. What went wrong?
    3. What could we do differently to improve?
  2. Outstanding tasks/work

    1. Expand
      titleImport/Export tickets

      Jira
      serverDuraSpace JIRA
      jqlQueryfilter=13801
      serverIdc815ca92-fd23-34c2-8fe3-956808caf8c5



    2. Expand
      titleImport/Export Verification tickets

      Jira
      serverDuraSpace JIRA
      jqlQueryfilter=14101
      serverIdc815ca92-fd23-34c2-8fe3-956808caf8c5


Notes

Retrospective
  1. Ben
    • well: pairing
    • wrong: challenge of speculating about future versioning
    • change: who to ask for feedback, availability of team
  2. Danny
    • well: pairing (youn wanted to be in hangouts earlier)
    • well: productive
    • wrong: not fully available
    • wrong: synchronizing import/export with verification
    • change: meeting on Friday of first week (Mon1/Wed1/Fri1/Tue2/Fri2)
  3. Esme
    • well: good and plenty of tickets
    • well: pairing
    • well: current meeting schedule was good
    • wrong: merge conflicts
    • wrong: f4 issues
    • wrong: synchronizing import/export with verification
    • change: smaller, more frequent sprints
  4. Harsha
    • wrong: did not fully participate
  5. Jim
    • well: productive and connected with team
    • wrong: not paired
    • wrong: not fully available
    • wrong: synchronizing import/export with verification
  6. Josh
    • well: productive, kudos to Danny
    • wrong: synchronizing import/export with verification
    • wrong: verification tool ended up in a broken state
    • change: verification sprint follows import/export sprint
    • change: would be good for there to be activity between sprints
  7. Longshou
    • well: pairing
    • well: focused on testing
  8. Andrew
    • wrong: too non-sprint many meetings
    • wrong: merging conflicts
    • change: do people read standups?
  9. General
    • maybe different timeframes for different roles
      • dev: 2week sprints
      • testing: 1week sprints
    • having pairing hangouts was helpful
  10. Mike - mail-in
    • well: pairing
    • productive
    • interest in working after sprint
  11. Youn - mail-in
    • wrong: two weeks too long
    • change: verification sprint follows import/export sprint
    • wanted to be in hangouts with danny/josh earlier

Standups

IRC Template

No Format
[Import/Export Standup]
Finished yesterday: 
  {ticket titles and associated JIRA links}
  {and/or brief textual description}
Working on today:
  {ticket titles and associated JIRA links}
  {and/or brief textual description}
Blockers:
  {brief textual description}

...