In order to properly scope pre-existing items for the 3.4 release, and ensure the quality/relevance of the items in the tracker, a multi-pass review of of the relevant issues in JIRA is planned.

First Pass: General Review

Who: Chris, Steve and Volunteers
When: Early April

For all Unresolved Issues:

Issues Reviewed:

Issues Needing Discussion:

Second Pass: Scoping for 3.4

Who: Steve and Chris
When: Early-Mid April

Note: At this point, it doesn't matter if we think the issues can be resolved in time for the release.  We're just saying they're "fair game" for 3.4.

For all Open bugs not assigned to a release (all Open Bugs):

For all Open Features or Improvements not assigned to a release (all Open Features or Improvements):

Third Pass: Assignments for 3.4

Who: Steve and Committers
When: Mid April

For all Open Issues scoped for 3.4: