Weeks run from Tuesday through to Monday of the following week, to coincide with the regular Committers Meeting on Tuesday of each week, during which activites of the previous week can be reviewed, and activities for the coming week can be planned.
Week |
Deadline |
Activity |
Apr 20 (Tue) - Apr 26 (Mon) |
Mon 26 April -Milestone 1 scheduled |
Release preparation/planning |
Apr 27 (Tue) - May 3 (Mon) |
|
Work on Milestone 1 items |
May 4 (Tue) - May 10 (Mon) |
|
Work on Milestone 1 items |
May 11 (Tue) - May 17 (Mon) |
Mon 17 May - Milestone 1 |
Work on Milestone 1 items |
May 18 (Tue) - May 24 (Mon) |
|
Work on Milestone 2 items |
May 25 (Tue) - May 31 (Mon) |
|
Work on Milestone 2 items |
Jun 1 (Tue) - Jun 7 (Mon) |
Mon 7 Jun - Milestone 2 |
Work on Milestone 2 items |
Jun 8 (Tue) - Jun 14 (Mon) |
|
Work on Milestone 3 items |
Jun 15 (Tue) - Jun 21 (Mon) |
|
Work on Milestone 3 items |
Jun 22 (Tue) - Jun 28 (Mon) |
Fri 25 Jun - Milestone 3 (code freeze) |
Work on Milestone 3 items |
Jun 29 (Tue) - Jul 5 (Mon) |
Fri 2 Jul - RC release |
Release week - final testing and release |
Jul 6 (Tue) - Jul 12 (Mon) |
|
OR2010 5-9 Jul |
Jul 13 (Tue) - Jul 19 (Mon) |
|
RC testing (community) |
Jul 20 (Tue) - Jul 26 (Mon) |
|
RC testing (community) |
Jul 27 (Tue) - Aug 2 (Mon) |
|
Bug fixes |
Aug 3 (Tue) - Aug 9 (Mon) |
|
Bug fixes |
Aug 10 (Tue) - Aug 16 (Mon) |
|
Bug fixes |
Aug 16 (Mon) - Aug 20 (Fri) |
Fri 20 Aug - 3.4 Release |
Release week - final testing and release |