Sprint Wrap Up

Attendees

General

Agenda

  1. Meta analysis of sprint process
  2. Summarize final state
  3. Walk through in-process and unstarted tickets
  4. Teeing up for next sprint

Minutes

Adam

  1. Would have liked to have Chris more involved
  2. Difficult to make estimates, but regular commits helped
  3. HTTP integration tests need help
  4. Helpful to write expectations on wiki: basing integration tests on this
  5. Document API in detail on wiki, with examples
  6. We could do better at developing a framework for testing
  7. Process

Frank

  1. Blocked by admins at SCC cluster
  2. Learned a bit about AWS
  3. Process has not made enough progress to make suggestions moving forward

Greg

  1. Scott discovered a delete issue
  2. Will be creating tickets for deletes
  3. Enjoyed working with Scott, new person on the team writing tests
  4. If you care enough about F4, acceptance testing is a minimum
  5. Would be helpful to inform local team of need for focus on sprint

Osman

  1. Finishing javadoc ticket
  2. Working on cluster tests in the background
  3. Would be good to document scripts/tests for automated cluster tests
  4. Having standing cluster for test would be helpful
  5. Institutional distractions are becoming less

Scott

  1. Finished delete tests
  2. Documentation is wrapped up
  3. Will be continuing performance testing tasks
  4. Spent beginning of sprint getting up to speed
  5. Worked on 3.7 patch
  6. Sprint reflection

Actions