Regular Attendees

  • Andrew (star)
  • Bill
  • Brad
  • Chris
  • Dan
  • Jonathan

General

  • Call In To: Free Conference Call HD - DuraCloud Line

    Please note that we will be using the Free Conference Call HD line for this call. Information about calling into this line is available from the link above.

  • (star) - Indicates who will be taking minutes

Discussion Topics

Planning Board
Task Board
DfR Planning and Estimating - 0.1

Topic

Discussion Leader

Tracking and Estimating Methodology

Jonathan

Review of Epics and ROM Estimates (Must be complete)

Dan

Kick-off Initial Stories

Brad and Dan

More stories and nothing but stories

No one gets out of this - Brad and Dan

List additional resources needed (perhaps a Git repo, addl mailing lists, bamboo build)

Chris

Coordination with DuraCloud builds, unit tests, ITs

Bill

Project and Partners

Jonathan

Actions from last meeting

Last meeting

Last Weeks Actions:

Action Item

Assignee

Status

Create a wiki page with story point listing for epics

Dan

(tick) (wiki)

Each of us submit number of story points for each of the epics over the next week

All

 

Tie some of the DuraCloud jira items to DfR stories

Bill + Andrew

 

Related Information
DfR Software Next Steps - Jan 2012
2012-01-03 - Architecture Meeting, Temple University

Status

  • Jonathan
    • Continued discussions with Fluid (overhead policy) and Thorny (public statements re collaboration)
    • Meeting with Sloan program officer tomorrow
  • Andrew
    • DuraCloud/Shib architecture updates
  • Bill
  • Brad
    • Unicon call
  • Chris
  • Dan
    • Discussed with Andrew the strawman approach to Jira and most of the team. (Andrew was the road)
    • Added a page for top-level estimates
    • Worked on adding cards (towards covering the whole project)
    • Met with Jonathan and Brad on priorities
  • Jonathan

Minutes

  1. Epic level planning and estimating
    • inputs from team complete
  2. Methodology
    • epics/stories/tasks
    • estimates are done at story-level
    • if a story is > 8pts, it is converted to an epic
    • need to add field in jira for story-points in 'tasks'
    • it will take more time (6 weeks?) to hone in on accurate velocity
  3. Scheduling
    • not all short-term stories have yet been created
    • approaches
      1. start working, and back-fill jira work (planning)
      2. do not start iteration until jira work for iteration is complete
    • suggestion
      1. get jiras populated for work in next two weeks out
      2. we come to next week's meeting with stories to review
    • need basic agreements: java6? scm? appserver?
    • define what each team member is planning on working on in short-term
    • discussed jira DFR-63 as an example
        • story-points 2?
        • Bill 3pts
        • Chris 2pts
    • Brad and I to put story points against security tasks
    • Dan and Chris to look at Object Creation Service
  4. Box account
    • monthly ?$
    • yearly $400
    • will create an account as soon as we are ready to use it

Actions

TBD