Regular Attendees

  • Bill 
  • Dan (star)
  • Danny 
  • Jonathan (Vacation)

General

Discussion Topic

TopicDiscussion Leader
SiDora UpdateDan
Review of Jira tasks in-progressBill

Status

  • Bill
  • Dan
    • See the email record on SIDora
      • We have a plan
      • We were notified that DG has a clean copy from SI
      • Perhaps we are getting closer to an AMI
    • Directory creation is nearly done. Remaining:
      • A good clean up (done, pushed)
      • Better code to prevent attempts to create directories twice (25% done)
      • Error and exception handling (maybe atomic ingest TBD) (25% done)
      • Choose/make a good content model in Sidora for directories (25% done)
      • Improve tests (Discussed with Bill) 75% done.
        • Only test what we use
        • Use "Sidora" Fedora for ITs to avoid having to add a Fedora deployment to the DfR Maven
        • There is no feasible way to set up DuraCloud (DuraStore) so use dfrtest for ITs
        • Still need to update some ITs particularly the DuraCloud to DfR IT
        • Purge in Fedora Client W/R/T Sidora Fedora not working (but in Admin client works)
        • I need to revise (decide) the strategy to permit adding a log message for ingest (the old one won't work)
      • Fix Bamboo build configuration (done, pushed)
    • Execution environment is integrated
    • Revised characterization task to use DROID by itself
  • Danny

Minutes

  • Sidora
    • We were notified that DG has a clean copy from SI
    • We hope to have an AMI this week
    • There are dependencies that will be affected next week if there is more delay
  • Review of Tasks
    • DFR-125 Sidora - See above
    • DFR-120 Directory Objects - 75% complete. See Dan's status
    • DFR-108 Characterization Metadata - Decided to use DuraCloud's DROID interface (and DROID) since is proves the point (new tools can be added later)
    • DFR-127 Java 7 - Substantially Complete.  Need to update Bamboo and POM
    • DFR-138 Enable Sidora Search Index - We need Sidora for this.  Even then we should start with the existing Sidora capabilities and just provide metadata for now
    • DFR-137 Datastream for DfR metadata - Bill will put into "In progress" state this week 
    • DFR-136 UpSync capture simple metadata - Danny will look and this and recommend an appropriate scope
    • DFR-126 Skin Sidora - We need the Sidora update to start but Danny's estimates that it will not take much time.  We have help available from DG if needed
    • DFR-109 Enhance Metadata - On hold and perhaps too large.  However, a small scope may be possible focused on built-in Sidora capabilities.  We will determine whether/what to include after most of the other tasks are ready for the demonstrations to be held in December.
    • DFR-91 UpSync - It is complete. Any improvements can be done in additional tasks.  It needs to be closed in Jira.
    • DFR-76 Checksums - Will be worked after DFR-137 provides us a place to put the data
  • Other Tasks
    • Dan took the action to add a README to the code and begin documenting the build/test/deploy configurations