Attendees

  • Alan Stanley
  • Amy Blau
  • Dana Bronson
  • Dara Virks
  • David Wilcox
  • Kun Lin
  • Paige Morfitt 

Agenda

Topic

Stand-up

  1. What has everyone been working on?
  2. What will you be working on over the next couple weeks?
  3. Are there any blockers that are preventing you from getting work done?
Production Migration Schedule

Priorities and areas of focus

  1. Timeline for remaining work
  2. Possible cut-over date
  3. Documentation tasks
Wrap-up and next steps

Notes

  1. Timeline for remaining collections
    1. Limited access collections are up on the server for testing
      1. Tests so far have worked well
    2. Larger collections are slower - down to 50 pages per hour
      1. Most decades of newspapers take about a day to ingest
      2. Javascript for making years and months collapsable is getting overwhelmed
        1. Very long page load times
        2. Short-term - instead of newspapers in huge collections we could break them down by decade
        3. May need a taxonomy term for Pioneer. Could be setup as a View.
          1. Newspaper vocabulary with taxonomy terms for each newspaper collection
          2. Publications could be given this term
  2. Workbench mitigation scripts
    1. Alan will share relevant scripts post-migration 

Actions