  1. Meta analysis of sprint process
  2. Summarize final state
  3. Walk through in-process and unstarted tickets
  4. Teeing up for next sprint

Minutes

  • Andrew
    • Standup notes are valuable as a log of what was worked on and how effort was spent.
      • Even better with more people on the sprint
    • Need a metric for determining if we are on track or not
      • Maybe use story points to estimate issues as we did in Pivotal
    • Document a format for daily sprint updates
  • Jon
    • Some tickets took longer than expected
    • Need to configure an IDE for debugging
    • Javadoc ticket took longer than expected
      • Useful for re-familiarizing with the codebase and processes
    • Would it help to evaluate participant’s experience with various technologies and assign tickets based on this?
  • Tickets
    • Jira
      serverDuraSpace JIRA
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverIdc815ca92-fd23-34c2-8fe3-956808caf8c5
      keyFCREPO-1556

      • Complete
    • Jira
      serverDuraSpace JIRA
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverIdc815ca92-fd23-34c2-8fe3-956808caf8c5
      keyFCREPO-1555

      • In progress
    • Jira
      serverDuraSpace JIRA
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverIdc815ca92-fd23-34c2-8fe3-956808caf8c5
      keyFCREPO-1507

      • Assigned to Esme
    • Jira
      serverDuraSpace JIRA
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverIdc815ca92-fd23-34c2-8fe3-956808caf8c5
      keyFCREPO-1294

      • Assigned to Aaron