TasksDurationStartEndStatus/Notes

Develop charter, requirements, resource feasibility, solicit participation,
approval of steering, project infrastructure, launch sub projects

3 weeks

2016-01-24

2016-02-13All complete except infrastructure. Mike Conlon working on this. On track.

Domain name, infrastructure hosting, stand up platform, three tier build,
branding

4 weeks

2016-02-02

2016-3-06Domain openvivo.org obtained. Infrastructure provider identified. Graham Triggs working on this. On track.

ORCiD authentication, Profile creation, ORCiD hook for DOI

6 days

TBA

TBAJim Blake will work on this. On track.
RDF generation for Journals (CrossRef) and Organizations (Grid)4 weeks2016-02-132016-03-13

Muhammad Javed will work with Mike Conlon on Journals. David Eichmann will work with Mike Conlon on Organizations. Alexandre Rademaker will also help.

Figshare Ingest4 weeks2016-02-132016-03-13Ted Lawless will work with Mike Conlon on this.
Publication Ingest from CrossRef with Attribution from user-entered DOI5 weeks2016-02-072016-03-12Graham Triggs is working on this. Prompt, fetch, confirm working. On track.
Full assembly – all features in place. Begin testing, begin remediation1 week2016-03-132016-03-19Tight coordination among team members needed here.
Remediation or additional features2 weeks2016-03-202016-04-02If things need to be fixed, fix them. If things need to be smoothed, smooth them. If things can be added, add them.

Final acceptance testing, refinement, communications, presentation materials

2 weeks

2015-04-03

2015-04-15 

Workshops and Visualizations Hackathon at Force 11 Conference

1 day2016-04-172016-04-17 

Additional Force11 demonstrations, continuous update of open VIVO from
Figshare and ORCiD, continuous export of data to GitHub, continuous import of data to Iowa repositories and tools.

2 days2016-04-182016-04-19 

 

...