TasksDurationStartEndStatus/Notes

Develop charter, requirements, resource feasibility, solicit participation, approval of steering, project infrastructure, launch sub projects

3 weeks

2016-01-24

2016-02-13Done. All in place. See Open VIVO Google Drive folder https://goo.gl/ofspSz

Domain name, infrastructure hosting, branding/theme, stand up platform, three tier build, branding

4 weeks

2016-02-02

2016-3-13

Domain

openvivo.org obtained. Infrastructure provider identified. Graham Triggs working on this. Paul Friedman and John Serafin will work on branding/UI for theme, profile and DOI ingest. Mike Conlon has identified fields that will be available for self-edit in Open VIVO.

, hosting, system in place. See http://openvivo.org Branding nearing completion

See https://goo.gl/MWsVNv

ORCiD authentication, Profile creation, ORCiD hook for DOI

6 days

TBA

TBAJim Blake will work on this
RDF generation for Journals (CrossRef and NLM)4 weeks2016-02-132016-03-13

Muhammad Javed and Violeta Ilik will work with Mike Conlon on Journals. Data model proposed. Data in hand. On track.

RDF generation for Organizations (Grid)4 weeks2016-02-132016-03-13Mike Conlon and Dave Eichmann will created RDF from the GRID data (http://grid.ac). Data in hand, repository created, data inspector created. See https://github.com/openvivo/grid-rdf.
Figshare Collection Ingest4 weeks2016-02-132016-03-13Ted Lawless, Mike Conlon and Simon Porter will work on this. Figshare now producing VIVO RDF. On track.
Identify and represent attribution/contribution4 weeks2016-02-132016-03-13Melissa Haendel, Kristi Holmes, Violeta Ilik and Alexandre Rademaker will work on this.
Publication Ingest from CrossRef with Attribution from user-entered DOI5 weeks2016-02-072016-03-13Substantially complete. Users can enter one or more DOI and/or one or more Pubmed IDs. VIVO fetches the metadata, presents to user for confirmation and association of role. Graham Triggs is working on this. On track.
Full assembly – all features in place. Begin testing, begin remediation, begin data export1 week2016-03-132016-03-19Tight coordination among team members needed here.
Remediation or additional features2 weeks2016-03-202016-04-02If things need to be fixed, fix them. If things need to be smoothed, smooth them. If things can be added, add them.
Harvest data from Open VIVO to CTSAsearch2 weeks2015-03-202015-04-02Dave Eichmann will work on this

Final acceptance testing, refinement, communications, presentation materials

2 weeks

2015-04-03

2015-04-15Stop adding things. Keep fixing things. Keep smoothing things.

Workshops and Visualizations Hackathon at Force 11 Conference

1 day2016-04-172016-04-17 

Additional Force11 demonstrations, continuous update of open VIVO from Figshare and ORCiD, continuous export of data to GitHub, continuous import of data to Iowa repositories and tools.

2 days2016-04-182016-04-19Conference attendees: Mike Conlon, Melissa Haendel, Kristi Holmes, Violeta Ilik, Dave Eichmann

 

...