Call in details:

Sprinters

Objectives

The objectives of sprint-04 are to:

  1. Test compatibility of exported Bags with:
    1. APTrust
    2. Perseids
    3. Archivematica (question)
  2. Test compatibility of import/export round-tripping between community and alternate Fedora implementations
  3. Import/export of versions
    1. Note: Want to keep upcoming Memento API alignment
  4. Lossless round-tripping (particularly dates)
    1. other round-tripping issues, e.g.:  FCREPO-2429 - Semantic differences between exports Open
  5. Resolve import bugs that were reported from v0.1 testing
  6. Verification tool
    1. Unicode-escaping when resources are exported leads to mismatch when those resources are re-imported
    2. Users are confused by the tool output
    3. Lower priority:
      1. Gracefully handling server-managed triples and timestamps that can't be updated
      2. Verifying Fedora-to-Fedora and disk-to-disk
      3. Anything special required for Bags?
  7. Lower-priority
    1. Importing into non-empty containers
      1. There may be several facets to this: importing into a container that already exists (other children of the same resource already exist) seems very useful, but syncing with an existing resource may be much more complex.  We should support the easy things, and be careful when tackling the more complex scenarios to maintain a good scope with stakeholder input.
    2. Maintain links in Bags with links to resources outside of Bags
      1. Revisit whether this is still an issue given the current Bag export/import functionality
    3. Incremental diffs of Bags, relating to sending updated Bags to preservation services, not re-transmitting large files that haven't changed, and not overwriting good content with content that's been corrupted, etc.
      1. Interesting functionality once the other functionality is solid

Resources

  • Design - Import - Export
  • Import / Export utility tickets

    type key summary assignee reporter priority status resolution created updated due

    Unable to locate Jira server for this macro. It may be due to Application Link configuration.

  • Import / Export verification tickets

    type key summary assignee reporter priority status resolution created updated due

    Unable to locate Jira server for this macro. It may be due to Application Link configuration.

Meetings

Meeting 01 - 2017-05-15

  • 9am ET

Attendees

Agenda

  1. Introductions
  2. Logistics
    1. Virtual daily stand-ups?
    2. IRC? 
    3. Conference calls?
    4. Email check-in?
    5. Sprint retrospective?
  3. Sprint Priorities
  4. Assign work

Minutes

  1. Kieran will be out the second week of the sprint
  2. Next meetings
    1. Wed 5/17 @10am ET
    2. Tues 5/23 @3pm ET
    3. Fri 5/19 @11am ET
  3. Dev teams
    1. Esmé and Longshou
    2. Mike and Ben
    3. Josh, Youn and Danny
  4. Testing / Docs teams
    1. Youn / Jim / Kieran / Bridget - detailed testing
  5. New tickets
    1. Import / Export between Fedora and Cavendish - Esmé
    2. Production roundtripping
      1. Duke - Jim
      2. Princeton - Esmé
      3. UMd - Josh
    3. Creation of small dataset for verification testing - Esmé
    4. Plan how versioning will be in line with Fedora specification
  6. Existing tickets
    1. Unable to locate Jira server for this macro. It may be due to Application Link configuration. - resolve with documentation and CND

    2. Longshou / Esmé
      1. Unable to locate Jira server for this macro. It may be due to Application Link configuration.
      2. ...
    3. Unable to locate Jira server for this macro. It may be due to Application Link configuration. - Josh
    4. Unable to locate Jira server for this macro. It may be due to Application Link configuration. - Danny
    5. Unable to locate Jira server for this macro. It may be due to Application Link configuration. - Josh
    6. Unable to locate Jira server for this macro. It may be due to Application Link configuration. - Danny to verify
    7. Unable to locate Jira server for this macro. It may be due to Application Link configuration. - Youn


Standups

IRC Template

[Import/Export Standup]
Finished yesterday: 
  {ticket titles and associated JIRA links}
  {and/or brief textual description}
Working on today:
  {ticket titles and associated JIRA links}
  {and/or brief textual description}
Blockers:
  {brief textual description}

 

...
  • No labels